- ##project.benefits.item.headline##at peak times 8,000 m² of slabs were formed, concreted and realised per week
- ##project.benefits.item.headline##reduced on-site material requirements plus cost savings thanks to coordination by PERI Project Manager in close cooperation with the Site Manager
Prosjektet
Bilder fra prosjektprosessen
##project.requirementsAndSolutions.headline##
Krav eller utfordringer
terminal shell with a construction schedule of just 12 months
huge volume of formwork and scaffolding material within the shortest period
due to static reasons, most of the slab areas had to be concreted in one pour together with the main and secondary beams
Løsninger
delivery of large quantities of materials optimised to the necessary on-site requirements
formwork and scaffolding solution for foundations, columns and slabs incl. beams
provision of a total of 2,700 pre-assembled slab tables delivered just-in-time to the construction site
appointment of a Project Manager to support the Site Manager in planning material requirements
Vis mer
Kundefordeler
at peak times 8,000 m² of slabs were formed, concreted and realised per week
reduced on-site material requirements plus cost savings thanks to coordination by PERI Project Manager in close cooperation with the Site Manager
Jürgen Feierle
Project Manager
With the PERI slab table solution at peak times we are realising 8,000 m² of slab formwork per week – with all beams and with floor heights of up to 7 m. By combining with SKYDECK we are even able to continue working in strong winds without interruption and can also minimise crane dependency. PERI construction site support offers us technical solutions in the shortest time and also supplies large volumes of materials within just 2 days.